BetaActiveSolarWindBatteryNWMTLBNL
500 MW hybrid in Yellowstone, MT · In queue since August 2020 · Proposed COD December 2023
500 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 4m
Schedule
27 months past proposed COD
Facilities Study50%
Queue EntryAug 13, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
MT
County
Yellowstone
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
500kV at Broadview Substation
Data Source
LBNL