— Project Summary

Queue ID
NWMT-378
Capacity
175 MW
Technology
Gas
Status
active
Location
Yellowstone, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveGasNWMTLBNL

175 MW generation in Yellowstone, MT · In queue since May 2020 · Proposed COD January 2023

175 MW

Capacity

1

Components

Gas

5y 10m

In Queue

Facility Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 8m

Schedule

39 months past proposed COD

Facilities Study50%
Queue EntryMay 8, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-01-01

Project Details

State

MT

County

Yellowstone

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

100kV at Laurel

Data Source

LBNL

No news available for this project.