175 MW generation in Yellowstone, MT · In queue since May 2020 · Proposed COD January 2023
175 MW
Capacity
1
Components
Gas
5y 10m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 8m
Schedule
39 months past proposed COD
Facilities Study50%
Queue EntryMay 8, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-01-01
Project Details
State
MT
County
Yellowstone
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
100kV at Laurel
Data Source
LBNL