BetaSuspendedGasNWMTLBNL
36 MW generation in Silver Bow, MT · In queue since May 2020 · Proposed COD July 2022
36 MW
Capacity
1
Components
Gas
5y 10m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 2m
Suspended25%
Queue EntryMay 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-07-01
Project Details
State
MT
County
Silver Bow
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
161kV at MHD
Data Source
LBNL