— Project Summary

Queue ID
NWMT-376
Capacity
58.8 MW
Technology
Battery
Status
suspended
Location
Yellowstone, MT
Region
West
Developer
IA Status
System Impact Study

BetaSuspendedBatteryNWMTLBNL

58.8 MW storage in Yellowstone, MT · In queue since May 2020 · Proposed COD October 2023

58.8 MW

Capacity

1

Components

Battery

5y 10m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 5m

Suspended25%
Queue EntryMay 6, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-10-01

Project Details

State

MT

County

Yellowstone

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

115kV at Baseline

Data Source

LBNL