BetaSuspendedSolarBatteryNWMTLBNL
200 MW hybrid in Deer Lodge, MT · In queue since March 2020 · Proposed COD February 2023
200 MW
Capacity
1
Components
Solar
6 years
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 11m
Suspended13%
Queue EntryMar 19, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-01
Project Details
State
MT
County
Deer Lodge
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV at Anaconda Mill Creek Substation
Data Source
LBNL
No news available for this project.