BetaSuspendedSolarBatteryNWMTLBNL
200 MW hybrid in Beaverhead, MT · In queue since October 2019 · Proposed COD April 2021
200 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 6m
Suspended50%
Queue EntryOct 9, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-04-01
Project Details
State
MT
County
Beaverhead
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV at Peterson Flats Substation
Data Source
LBNL
No news available for this project.