— Project Summary

Queue ID
NWMT-366
Capacity
600 MW
Technology
Wind
Status
active
Location
Rosebud, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindNWMTLBNL

600 MW generation in Rosebud, MT · In queue since September 2019 · Proposed COD December 2022

600 MW

Capacity

1

Components

Wind

6y 6m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

40 months past proposed COD

Facilities Study50%
Queue EntrySep 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

MT

County

Rosebud

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Colstrip 500kV Substation

Data Source

LBNL

No news available for this project.