300.15 MW generation in Wheatland, MT · In queue since April 2019 · Proposed COD October 2022
300.15 MW
Capacity
1
Components
Wind
6y 11m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 6m
Schedule
41 months past proposed COD
Facilities Study50%
Queue EntryApr 24, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-10-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL