— Project Summary

Queue ID
NWMT-362
Capacity
300.15 MW
Technology
Wind
Status
active
Location
Wheatland, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindNWMTLBNL

300.15 MW generation in Wheatland, MT · In queue since April 2019 · Proposed COD October 2022

300.15 MW

Capacity

1

Components

Wind

6y 11m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 6m

Schedule

41 months past proposed COD

Facilities Study50%
Queue EntryApr 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

MT

County

Wheatland

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

New proposed 500kV Substation between Broadview and Townsend

Data Source

LBNL

No news available for this project.