— Project Summary

Queue ID
NWMT-361
Capacity
600 MW
Technology
Wind
Status
active
Location
Wheatland, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindNWMTLBNL

600 MW generation in Wheatland, MT · In queue since March 2019 · Proposed COD December 2021

600 MW

Capacity

1

Components

Wind

7 years

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 9m

Schedule

52 months past proposed COD

Facilities Study50%
Queue EntryMar 15, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

MT

County

Wheatland

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

New proposed 500kV Substation between Broadview and Townsend

Data Source

LBNL