— Project Summary

Queue ID
NWMT-360
Capacity
200 MW
Technology
Wind
Status
suspended
Location
Wheatland, MT
Region
West
Developer
IA Status
System Impact Study

BetaSuspendedWindNWMTLBNL

200 MW generation in Wheatland, MT · In queue since February 2019 · Proposed COD December 2021

200 MW

Capacity

1

Components

Wind

7y 1m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 10m

Suspended25%
Queue EntryFeb 14, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

MT

County

Wheatland

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

230kV at Judith Gap Auto

Data Source

LBNL

No news available for this project.