— Project Summary

Queue ID
NWMT-356
Capacity
750 MW
Technology
Wind
Status
active
Location
Rosebud, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindNWMTLBNL

750 MW generation in Rosebud, MT · In queue since October 2018 · Proposed COD September 2021

750 MW

Capacity

1

Components

Wind

7y 5m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 11m

Schedule

56 months past proposed COD

Facilities Study50%
Queue EntryOct 9, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-09-01

Project Details

State

MT

County

Rosebud

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

500kV at Colstrip Substation

Data Source

LBNL

No news available for this project.