BetaActiveWindNWMTLBNL
750 MW generation in Rosebud, MT · In queue since October 2018 · Proposed COD September 2021
750 MW
Capacity
1
Components
Wind
7y 5m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 11m
Schedule
56 months past proposed COD
Facilities Study50%
Queue EntryOct 9, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-09-01
Project Details
State
MT
County
Rosebud
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
500kV at Colstrip Substation
Data Source
LBNL
No news available for this project.