20 MW hybrid in Yellowstone, MT · In queue since March 2018 · Proposed COD June 2021
20 MW
Capacity
1
Components
Solar
8 years
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3y 3m
Schedule
59 months past proposed COD
Facilities Study50%
Queue EntryMar 5, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-06-01
Project Details
State
MT
County
Yellowstone
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
161kV line at Alkali Creek Substation
Data Source
LBNL