BetaSuspendedWindBatteryNWMTLBNL
80 MW hybrid in Wheatland, MT · In queue since September 2017 · Proposed COD October 2024
80 MW
Capacity
1
Components
Wind
8y 6m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
7y 1m
Suspended50%
Queue EntrySep 25, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV Line from Judith Gap Auto to Judith Gap South
Data Source
LBNL
No news available for this project.