— Project Summary

Queue ID
NWMT-311
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Yellowstone, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryNWMTLBNL

300 MW hybrid in Yellowstone, MT · In queue since February 2017 · Proposed COD December 2021

300 MW

Capacity

1

Components

Solar

9y 1m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 10m

Schedule

52 months past proposed COD

Facilities Study50%
Queue EntryFeb 27, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

MT

County

Yellowstone

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

500kV at Broadview Substation

Data Source

LBNL

No news available for this project.