BetaSuspendedOther StorageNWMTLBNL
450 MW storage in Meagher, MT · In queue since December 2016 · Proposed COD February 2023
450 MW
Capacity
1
Components
Other Storage
9y 3m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 2m
Suspended50%
Queue EntryDec 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-01
Project Details
State
MT
County
Meagher
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
New 500kV Substation between Broadview and Townsend
Data Source
LBNL
No news available for this project.