— Project Summary

Queue ID
NWMT-309
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Yellowstone, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryNWMTLBNL

80 MW hybrid in Yellowstone, MT · In queue since December 2016 · Proposed COD March 2022

80 MW

Capacity

1

Components

Solar

9y 3m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

5y 3m

Schedule

49 months past proposed COD

Facilities Study50%
Queue EntryDec 9, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-03-31

Project Details

State

MT

County

Yellowstone

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

230kV at Broadview Substation

Data Source

LBNL

No news available for this project.