80 MW hybrid in Yellowstone, MT · In queue since December 2016 · Proposed COD March 2022
80 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5y 3m
Schedule
49 months past proposed COD
Facilities Study50%
Queue EntryDec 9, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-03-31
Project Details
State
MT
County
Yellowstone
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV at Broadview Substation