BetaActiveWindBatteryNWMTLBNL
315 MW hybrid in Stillwater, MT · In queue since July 2016 · Proposed COD August 2020
315 MW
Capacity
1
Components
Wind
9y 8m
In Queue
Facility Study
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
4y 1m
Schedule
68 months past proposed COD
Facilities Study50%
Queue EntryJul 11, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-08-15
Project Details
State
MT
County
Stillwater
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV Line between Wilsall and Columbus Rapelje Substations
Data Source
LBNL