— Project Summary

Queue ID
NWMT-300
Capacity
315 MW
Technology
Wind+Battery
Status
active
Location
Stillwater, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBatteryNWMTLBNL

315 MW hybrid in Stillwater, MT · In queue since July 2016 · Proposed COD August 2020

315 MW

Capacity

1

Components

Wind

9y 8m

In Queue

Facility Study

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

4y 1m

Schedule

68 months past proposed COD

Facilities Study50%
Queue EntryJul 11, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-08-15

Project Details

State

MT

County

Stillwater

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

230kV Line between Wilsall and Columbus Rapelje Substations

Data Source

LBNL

No news available for this project.