BetaActiveBatteryNVELBNL
500 MW storage in Washoe, NV · In queue since March 2024 · Proposed COD September 2028
500 MW
Capacity
1
Components
Battery
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
In Study38%
Queue EntryMar 21, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
NV
County
Washoe
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.