— Project Summary

Queue ID
NVE-Company QH
Capacity
199.9 MW
Technology
Battery
Status
active
Location
White Pine, NV
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryNVELBNL

199.9 MW storage in White Pine, NV · In queue since September 2023 · Proposed COD January 2026

199.9 MW

Capacity

1

Components

Battery

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 4m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 25, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

NV

County

White Pine

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.