200 MW hybrid in Esmeralda, NV · In queue since March 2023 · Proposed COD December 2026
200 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 9m
In Study38%
Queue EntryMar 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
NV
County
Esmeralda
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL