BetaSuspendedBatteryNVELBNL
500 MW storage in Lyon, NV · In queue since January 2023 · Proposed COD November 2028
500 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Suspended
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 10m
Suspended38%
Queue EntryJan 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NV
County
Lyon
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL