BetaSuspendedBatteryNVELBNL
500 MW storage in Lander, NV · In queue since January 2023 · Proposed COD December 2035
500 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Suspended
IA Status
COD target: 2035
Interconnection Timeline
Total Duration
12y 11m
Suspended38%
Queue EntryJan 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2035-12-31
Project Details
State
NV
County
Lander
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.