— Project Summary

Queue ID
NVE-Company OG
Capacity
550 MW
Technology
Solar+Battery
Status
suspended
Location
Lander, NV
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryNVELBNL

550 MW hybrid in Lander, NV · In queue since January 2023 · Proposed COD December 2028

550 MW

Capacity

1

Components

Solar

3y 2m

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 11m

Suspended38%
Queue EntryJan 9, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NV

County

Lander

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.