— Project Summary

Queue ID
NVE-Company NS
Capacity
300 MW
Technology
Solar+Battery
Status
suspended
Location
Eureka, NV
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryNVELBNL

300 MW hybrid in Eureka, NV · In queue since September 2022 · Proposed COD November 2029

300 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Suspended

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 2m

Suspended38%
Queue EntrySep 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-15

Project Details

State

NV

County

Eureka

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.