— Project Summary

Queue ID
NVE-Company NJ
Capacity
200 MW
Technology
Battery
Status
active
Location
Storey, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryNVELBNL

200 MW storage in Storey, NV · In queue since March 2022 · Proposed COD June 2026

200 MW

Capacity

1

Components

Battery

4 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 3m

Construction75%
Queue EntryMar 30, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

NV

County

Storey

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.