100 MW storage in Washoe, NV · In queue since March 2022 · Proposed COD April 2024
100 MW
Capacity
1
Components
Battery
4 years
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 1m
Suspended38%
Queue EntryMar 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
NV
County
Washoe
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.