— Project Summary

Queue ID
NVE-Company NH
Capacity
100 MW
Technology
Battery
Status
suspended
Location
Washoe, NV
Region
West
Developer
IA Status
Suspended

BetaSuspendedBatteryNVELBNL

100 MW storage in Washoe, NV · In queue since March 2022 · Proposed COD April 2024

100 MW

Capacity

1

Components

Battery

4 years

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 1m

Suspended38%
Queue EntryMar 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-01

Project Details

State

NV

County

Washoe

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.