BetaSuspendedSolarBatteryNVELBNL
300 MW hybrid in Lander, NV · In queue since March 2022 · Proposed COD December 2030
300 MW
Capacity
1
Components
Solar
4 years
In Queue
Suspended
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
8y 9m
Suspended38%
Queue EntryMar 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-31
Project Details
State
NV
County
Lander
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.