— Project Summary

Queue ID
NVE-Company MY
Capacity
715 MW
Technology
Wind
Status
suspended
Location
Lassen, CA
Region
West
Developer
IA Status
Suspended

BetaSuspendedWindNVELBNL

715 MW generation in Lassen, CA · In queue since March 2022 · Proposed COD December 2032

715 MW

Capacity

1

Components

Wind

4 years

In Queue

Suspended

IA Status

COD target: 2032

Interconnection Timeline

Total Duration

10y 9m

Suspended38%
Queue EntryMar 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2032-12-31

Project Details

State

CA

County

Lassen

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL