— Project Summary

Queue ID
NVE-Company MN
Capacity
1.3 MW
Technology
Solar
Status
active
Location
Lyon, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarGeothermalNVELBNL

1.3 MW hybrid in Lyon, NV · In queue since December 2021 · Proposed COD June 2022

1.3 MW

Capacity

1

Components

Solar

4y 3m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

6 months

Schedule

46 months past proposed COD

Construction75%
Queue EntryDec 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2022-06-01

Project Details

State

NV

County

Lyon

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.