BetaSuspendedSolarBatteryNVELBNL
300 MW hybrid in Lyon, NV · In queue since September 2021 · Proposed COD December 2029
300 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Suspended
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 3m
Suspended38%
Queue EntrySep 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
NV
County
Lyon
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.