— Project Summary

Queue ID
NVE-Company MH
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Churchill, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryNVELBNL

300 MW hybrid in Churchill, NV · In queue since September 2021 · Proposed COD September 2024

300 MW

Capacity

1

Components

Solar

4y 6m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

19 months past proposed COD

Construction75%
Queue EntrySep 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2024-09-01

Project Details

State

NV

County

Churchill

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.