BetaActiveSolarBatteryNVELBNL
300 MW hybrid in White Pine, NV · In queue since September 2021 · Proposed COD December 2028
300 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 3m
Construction75%
Queue EntrySep 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
NV
County
White Pine
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.