— Project Summary

Queue ID
NVE-Company LW
Capacity
550 MW
Technology
Solar+Battery
Status
suspended
Location
Mineral, NV
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryNVELBNL

550 MW hybrid in Mineral, NV · In queue since September 2021 · Proposed COD December 2029

550 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Suspended

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 3m

Suspended38%
Queue EntrySep 29, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

NV

County

Mineral

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.