600 MW hybrid in White Pine, NV · In queue since September 2021 · Proposed COD October 2025
600 MW
Capacity
1
Components
Wind
4y 6m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 1m
Suspended38%
Queue EntrySep 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
NV
County
White Pine
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.