— Project Summary

Queue ID
NVE-Company LT
Capacity
40 MW
Technology
Other
Status
active
Location
Lander, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveGeothermalNVELBNL

40 MW generation in Lander, NV · In queue since September 2021 · Proposed COD January 2026

40 MW

Capacity

1

Components

Geothermal

4y 6m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 4m

Schedule

3 months past proposed COD

Construction75%
Queue EntrySep 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

NV

County

Lander

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.