— Project Summary

Queue ID
NVE-Company LR
Capacity
29 MW
Technology
Other
Status
active
Location
Lander, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveGeothermalNVELBNL

29 MW generation in Lander, NV · In queue since September 2021 · Proposed COD December 2024

29 MW

Capacity

1

Components

Geothermal

4y 6m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

15 months past proposed COD

Construction75%
Queue EntrySep 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

NV

County

Lander

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.