— Project Summary

Queue ID
NVE-Company LK
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Lyon, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryNVELBNL

200 MW hybrid in Lyon, NV · In queue since March 2021 · Proposed COD December 2029

200 MW

Capacity

1

Components

Solar

5 years

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 9m

Construction75%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

NV

County

Lyon

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL