— Project Summary

Queue ID
NVE-Company LF
Capacity
300 MW
Technology
Wind
Status
suspended
Location
Lassen, CA
Region
West
Developer
IA Status
Suspended

BetaSuspendedWindNVELBNL

300 MW generation in Lassen, CA · In queue since March 2021 · Proposed COD September 2023

300 MW

Capacity

1

Components

Wind

5 years

In Queue

Suspended

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 6m

Suspended38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-01

Project Details

State

CA

County

Lassen

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.