BetaSuspendedWindNVELBNL
300 MW generation in Lassen, CA · In queue since March 2021 · Proposed COD September 2023
300 MW
Capacity
1
Components
Wind
5 years
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 6m
Suspended38%
Queue EntryMar 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-01
Project Details
State
CA
County
Lassen
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL