— Project Summary

Queue ID
NVE-Company LB
Capacity
115 MW
Technology
Other
Status
suspended
Location
Pershing, NV
Region
West
Developer
IA Status
Suspended

BetaSuspendedGeothermalNVELBNL

115 MW generation in Pershing, NV · In queue since March 2021 · Proposed COD December 2029

115 MW

Capacity

1

Components

Geothermal

5 years

In Queue

Suspended

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 9m

Suspended38%
Queue EntryMar 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

NV

County

Pershing

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.