BetaActiveGeothermalNVELBNL
4.8 MW generation in Lyon, NV · In queue since September 2020 · Proposed COD October 2027
4.8 MW
Capacity
1
Components
Geothermal
5y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 1m
Construction75%
Queue EntrySep 17, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
NV
County
Lyon
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.