BetaActiveBatteryNVELBNL
50 MW storage in Carson City, NV · In queue since March 2019 · Proposed COD September 2023
50 MW
Capacity
1
Components
Battery
7 years
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 6m
Schedule
30 months past proposed COD
Construction75%
Queue EntryMar 25, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-09-30
Project Details
State
NV
County
Carson City
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL