BetaActiveSolarBatteryNVELBNL
200 MW hybrid in Washoe, NV · In queue since March 2018 · Proposed COD February 2027
200 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 11m
Construction75%
Queue EntryMar 29, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
NV
County
Washoe
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.