BetaActiveSolarNVELBNL
80 MW generation in Pershing, NV · In queue since March 2018 · Proposed COD June 2021
80 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3y 3m
Schedule
59 months past proposed COD
Construction75%
Queue EntryMar 19, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2021-06-01
Project Details
State
NV
County
Pershing
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.