— Project Summary

Queue ID
NVE-Company IF
Capacity
350 MW
Technology
Solar
Status
active
Location
Humboldt, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarNVELBNL

350 MW generation in Humboldt, NV · In queue since March 2018 · Proposed COD February 2026

350 MW

Capacity

1

Components

Solar

8 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 11m

Schedule

2 months past proposed COD

Construction75%
Queue EntryMar 19, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-02-01

Project Details

State

NV

County

Humboldt

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.