BetaSuspendedSolarBatteryNVELBNL
240 MW hybrid in Pershing, NV · In queue since September 2017 · Proposed COD August 2024
240 MW
Capacity
1
Components
Solar
8y 6m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
6y 11m
Suspended38%
Queue EntrySep 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-01
Project Details
State
NV
County
Pershing
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.