BetaActiveGeothermalNVELBNL
45 MW generation in Washoe, NV · In queue since August 2017 · Proposed COD January 2026
45 MW
Capacity
1
Components
Geothermal
8y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 5m
Schedule
2 months past proposed COD
Construction75%
Queue EntryAug 15, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2026-01-31
Project Details
State
NV
County
Washoe
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.