38.5 MW generation in Churchill, NV · In queue since April 2010 · Proposed COD September 2026
38.5 MW
Capacity
1
Components
Geothermal
15y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
16y 5m
Construction75%
Queue EntryApr 14, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
NV
County
Churchill
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.