— Project Summary

Queue ID
NVE-Company 253
Capacity
169 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryNVELBNL

169 MW hybrid in Clark, NV · In queue since June 2023 · Proposed COD May 2029

169 MW

Capacity

1

Components

Solar

2y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 11m

In Study38%
Queue EntryJun 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-01

Project Details

State

NV

County

Clark

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL

No news available for this project.