220 MW storage in Clark, NV · In queue since January 2022 · Proposed COD May 2029
220 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 4m
Construction75%
Queue EntryJan 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2029-05-01