— Project Summary

Queue ID
NVE-Company 197
Capacity
200 MW
Technology
Battery
Status
active
Location
Clark, NV
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryNVELBNL

200 MW storage in Clark, NV · In queue since March 2021 · Proposed COD June 2024

200 MW

Capacity

1

Components

Battery

5 years

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

22 months past proposed COD

Construction75%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

NV

County

Clark

Region

West

Developer

Utility

NV Energy

Entity

NVE

Data Source

LBNL